NLA Arbitration Newsletter

Arbitration Newsletter — February 2025

Covering Supreme Court and High Court rulings on limitation law and arbitration challenges, kompetenz-kompetenz under Section 11, procedural requirements under Section 8, seat versus venue jurisdiction, and the limited scope of judicial interference under Section 34.

NLA Arbitration Newsletter — February 2025

My Preferred Transformation & Hospitality (P) Ltd. v. Faridabad Implements (P) Ltd., 2025 SCC OnLine SC 70

Supreme Court — Court raises concerns over the stringent application of limitation laws to arbitration challenges, calls on the Legislature to clarify ambiguities in the Arbitration Act.

The case revolved around an appeal filed by the Petitioners, challenging a Delhi High Court decision that dismissed their application to set aside an arbitral award on the ground of limitation. The dispute arose from lease agreements between the Petitioners and the Respondent, culminating in an arbitral award in favour of the Respondent on February 4, 2022. The Petitioners received the signed award on February 14, 2022, marking the commencement of the limitation period. The statutory three-month period to challenge the award expired on May 29, 2022, but an additional 30-day condonable period was available under the proviso to Section 34(3). This period ended on June 28, 2022, during the Delhi High Court’s summer vacation. The Petitioners filed their application on July 4, 2022, the court’s first working day after reopening. However, the High Court dismissed the application as time-barred, and its division bench upheld this decision.

The Petitioners argued before the Supreme Court that Section 10 of the General Clauses Act, 1897, which allows for filing on the next working day if a deadline falls on a holiday, should apply to the additional 30-day condonable period under Section 34(3). The Supreme Court disagreed, emphasizing that the Limitation Act governs such cases and dismissed the appeal. The Court noted that Section 34(3) of the Arbitration and Conciliation Act prescribes a strict three-month limitation period for challenging arbitral awards, with an additional 30-day condonable period provided under its proviso. However, the Court observed that these provisions do not expressly or impliedly exclude the application of Section 4 of the Limitation Act, which allows filing on the next working day if the prescribed period expires on a court holiday. The Bench criticized the rigid interpretation of limitation provisions, which equates the “prescribed period” under Section 4 and Section 29(2) of the Limitation Act solely with the three-month period under Section 34(3), excluding the additional 30 days.

The Court underscored the importance of adopting a liberal approach to limitation statutes in arbitration cases. Remedies under Sections 34 and 37 of the Arbitration Act, which allow parties to challenge arbitral awards and appeal decisions, are already limited by statutory design. A rigid application of limitation laws further curtails these remedies, discouraging parties from opting for arbitration as a dispute resolution mechanism. The Court expressed concern over the judicial tendency to interpret the applicability of Sections 4 to 24 of the Limitation Act on a case-to-case basis, rather than relying on clear statutory prescriptions. This inconsistency stems from the Supreme Court’s earlier ruling in Union of India v. Popular Construction Co., (2001) 8 SCC 470, which held that the proviso to Section 34(3) “impliedly” excludes Section 5 of the Limitation Act. Such implied exclusions create uncertainty, leaving the application of limitation provisions at the discretion of courts.

The Supreme Court ultimately dismissed the appeal, holding that the Petitioners had filed their application beyond the permissible period. It clarified that Section 4 of the Limitation Act applies only to the initial three-month period under Section 34(3) of the Arbitration Act and not to the additional 30-day condonable period. While affirming the existing legal framework, the Court highlighted the need for a more flexible approach to limitation laws to preserve the limited remedies available to parties under the Arbitration Act. It concluded by calling for legislative action to address these issues and ensure arbitration remains a viable and effective dispute resolution method.

Key Takeaway

The aspect of limitation with regards to Section 11 of the Arbitration Act was recently addressed by the Supreme Court in Arif Azim Co. Ltd. v. Aptech Ltd., where the Court held that Article 137 of the Limitation Act, which provides a three-year limitation period from the date the right to apply accrues, applies to Section 11(6) applications for appointment of arbitrators. The Court’s call for legislative clarity signals that parties should not assume ambiguous limitation provisions will be read liberally; timely filing remains paramount.

Shreegopal Barasia v. Creative Homes, 2025 SCC OnLine Bom 42

Bombay High Court — Court clarifies that substantive objections on the existence or validity of an arbitration agreement must be adjudicated by the Arbitral Tribunal under Section 16, not by courts under Section 11.

The petition, filed under Section 11 of the Arbitration and Conciliation Act, 1996, sought to refer disputes to arbitration arising from two agreements: an agreement dated February 19, 2007, and a deed dated August 14, 2015, which cancelled the earlier agreement. The Respondents opposed the referral, raising substantive objections. They argued that Respondent No. 2, a partner of Respondent No. 1 (a partnership firm), lacked implied authority to bind the firm to an arbitration clause under the agreements. It was contended that under Section 19(2)(a) of the Indian Partnership Act, 1933, a partner cannot submit disputes to arbitration without explicit authorization. Additionally, the Respondents contended that the arbitration agreement did not expressly empower the Arbitral Tribunal to determine the existence or validity of the agreement.

The Court noted that Section 16(1) of the Arbitration and Conciliation Act allows the Arbitral Tribunal to rule on its own jurisdiction, including objections concerning the existence or validity of an arbitration agreement. The arbitration clause is treated as an independent agreement, separate from the main contract. Consequently, even if the main contract is deemed void, the arbitration clause may remain valid. The Court emphasized that the scope of judicial intervention under Section 11 is limited to ensuring the existence of an arbitration agreement, while substantive objections concerning the agreement’s validity or existence must be adjudicated by the Arbitral Tribunal under Section 16. The Court relied on the Supreme Court’s judgment in Ajay Madhusudan Patel v. Jyotrindra S. Patel, 2024 SCC OnLine SC 2597, which held that courts under Section 11 must only determine the existence of an arbitration agreement as per Section 7 of the Act.

The Court observed that Section 19(2)(a) of the Partnership Act restricts a partner from submitting disputes to arbitration without explicit authorization from other partners. However, whether a custom or trade usage permitted arbitration would also need to be considered, and these substantive issues should be determined by the tribunal. The Court referred to the Supreme Court’s judgment in Interplay Between Arbitration Agreements under Arbitration, 1996 & Stamp Act, 1899, In re, (2024) 6 SCC 1, which held that the referral court under Section 11 must restrict its examination to the existence of an arbitration agreement. The Bombay High Court concluded that the arbitration clause existed, the Respondents’ objections did not warrant judicial intervention, and allowed the petition, appointing an arbitrator to adjudicate the disputes.

Key Takeaway

The principle of Kompetenz-Kompetenz empowers Arbitral Tribunals to rule on their own jurisdiction, including any objections regarding the existence or validity of the arbitration agreement. In India, this principle is enshrined in Section 16 of the Arbitration and Conciliation Act, 1996. It ensures that tribunals can determine their jurisdiction without undue interference from courts, thereby promoting the autonomy and efficiency of the arbitration process.

Smt. Gitarani Maity v. Mrs. Krishna Chakraborty and others, 2025 Cal HC 308

Calcutta High Court — Court clarifies that civil courts retain jurisdiction to adjudicate suits on merits where no timely application for reference to arbitration is made under Section 8, and that Section 8 does not empower courts to dismiss a suit outright.

The appellant challenged the Trial Judge’s judgment and decree, which allowed an application filed by the Respondent under Section 8 of the Arbitration and Conciliation Act, 1996, to refer the dispute to arbitration. The appellant contended that Section 8 does not provide for the dismissal of a civil suit but merely permits the court to refer the matter to arbitration upon a valid application. Additionally, the Respondent had failed to file the application under Section 8 either simultaneously with or prior to the submission of the written statement, violating the procedural requirement under Section 8. The Respondent relied on the Delhi High Court’s judgment in Madhu Sudan Sharma v. Omaxe Ltd., 2023 SCC OnLine Del 7136, to argue that even if no formal application under Section 8 is filed, an objection to jurisdiction based on the existence of an arbitration clause in the written statement is sufficient to warrant a reference to arbitration.

The Court emphasized that Section 8 requires a party seeking reference to arbitration to file an application before or simultaneously with the submission of their first written statement. This procedural safeguard ensures that parties do not delay invoking arbitration to frustrate or derail the adjudication process in civil courts. The Bench declined to follow the Delhi High Court’s judgment in Madhu Sudan Sharma. Instead, the Court relied on the Supreme Court’s judgment in Sukanya Holdings (P) Ltd. v. Jayesh H. Pandya, (2003) 5 SCC 531, which unequivocally held that the application under Section 8 must precede or accompany the written statement.

The Court reiterated that civil courts are competent to entertain and adjudicate suits on merits unless a valid and timely application under Section 8 is made. The High Court identified two critical errors in the Trial Judge’s approach: the Trial Judge dismissed the suit outright under Section 8, which is not contemplated by the provision (Section 8 merely provides for a reference to arbitration, not dismissal); and the Trial Judge entertained the Section 8 application even though it was filed after the Respondent’s first written statement. The Calcutta High Court allowed the appeal and dismissed the Section 8 application, reaffirming civil court jurisdiction.

Key Takeaway

Section 8 of the Arbitration and Conciliation Act, 1996, mandates that a judicial authority must refer parties to arbitration if a valid arbitration agreement exists and a party applies for such a reference no later than submitting their first statement on the substance of the dispute. An application filed after the first written statement is inadmissible. The provision only enables a reference to arbitration — it does not authorize dismissal of the suit, which must be stayed rather than terminated.

Versatile Construction v. Tata Motors Finance Ltd., 2025 Cal HC 15

Calcutta High Court — Court clarifies the distinction between the “seat” and “venue” of arbitration, holding that an expressly designated seat carries exclusive jurisdiction for all arbitration-related proceedings.

Versatile Construction (Appellant) entered into a hire-purchase agreement with Tata Motors Finance Ltd. (Respondent) for purchasing a Dumper vehicle. The Appellant received a loan of INR 42,16,095 and repaid INR 28,23,796. The Respondent invoked the arbitration clause after sending a notice to the Appellant on June 19, 2022. The Appellant chose not to participate, leading to an ex-parte arbitral award on September 9, 2024. Subsequently, the Appellant filed an application under Sections 9 and 34 of the Arbitration and Conciliation Act, 1996, challenging the award. A single judge ruled that as per the agreement, Mumbai had exclusive jurisdiction, and the Calcutta High Court lacked territorial jurisdiction. The Appellant appealed this decision.

The Court referred to the Shashoua Principle, which states that an expressly designated “venue” in the absence of an alternative seat, combined with a supranational body of arbitration rules, establishes the venue as the juridical seat of arbitration. The Court also relied on several Supreme Court precedents, including Bharat Aluminium Co. v. Kaiser Aluminium Technical Services Inc., (2012) 9 SCC 552, and BGS SGS SOMA JV v. NHPC, (2020) 4 SCC 234, which clarified that once the seat is selected, it amounts to an exclusive jurisdiction clause. In Mankastu Impex (P) Ltd. v. Airvisual Ltd., (2020) 5 SCC 399, the Supreme Court held that the seat of arbitration determines which court has supervisory authority over the proceedings.

The Court observed that the arbitration clause (Clause 21.1) in the loan agreement stated that arbitration was to be held in Mumbai as per the Arbitration and Conciliation Act, 1996, and Clause 22 vested jurisdiction in the competent courts and tribunals in Mumbai. Based on these clauses, the Court concluded that Mumbai was both the venue and the seat of arbitration. The principal civil court of original jurisdiction in Mumbai or the Bombay High Court would have supervisory jurisdiction under Sections 34 and 37 of the Act. The Calcutta High Court reaffirmed that an express designation of the seat of arbitration in an agreement grants exclusive jurisdiction to the courts at the seat, dismissing the appeal.

Key Takeaway

The Shashoua Principle, arising from Roger Shashoua v. Mukesh Sharma, 2009 EWHC 957 (Comm), holds that an expressly designated “venue” in the absence of an alternative seat, combined with a supranational body of arbitration rules, establishes the venue as the juridical seat. Once the seat is designated, it confers exclusive jurisdiction on the courts at that seat — overriding any concurrent jurisdiction theory. Parties must draft arbitration clauses with precision, as any express seat designation will determine the exclusive supervisory court for all post-award challenges.

Center for Research Planning and Action v. National Medicinal Plants Board, Ministry of AYUSH, Government of India, 2025/DHC/0042

Delhi High Court — Court emphasizes the limited scope of judicial interference under Section 34, reinstating an arbitral award that a Single Judge had set aside for alleged patent illegality.

The appellant, a data service provider, was engaged by the respondent — an organization under the Government of India — to collect, organize, and analyse data related to Ayurveda, Sidha, and Unani (ASU) drug manufacturers. After an amendment to the Drugs and Cosmetics Rules, 1945, ASU drug manufacturers were required to maintain records of raw materials used and submit them to State Drug Licensing Authorities. While the respondent undertook to provide a list of 8,000 units to commence work, it later emerged that no such list had been maintained. The appellant had to independently identify approximately 31,000 potential units, incurring significant additional expenses. Disputes arose over delays and additional costs, leading to arbitration proceedings. The Arbitrator ruled in favor of the appellant, finding that the respondent’s failure to provide the necessary information had frustrated the contract. The respondent challenged the arbitral award under Section 34, claiming it was patently illegal, and a Single Judge set aside the award, prompting the appellant to appeal under Section 37.

The Court reiterated that an arbitral award can only be set aside on specific grounds under Section 34(2) and Section 34(3) of the Arbitration Act, such as contravention of public policy, fraud, corruption, or fundamental violations of Indian law. In MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163, the Supreme Court clarified that courts cannot re-evaluate evidence or substitute their views for that of the arbitrator. Referring to NHAI v. M. Hakeem, (2021) 9 SCC 1, the Court emphasized that Section 34 does not empower courts to modify an arbitral award. The arbitral tribunal’s decision was based on a detailed examination of the evidence and the principle of unjust enrichment. The Court observed that a tribunal’s findings, especially when based on expert knowledge, should not be lightly interfered with. The Court held that the award was not in conflict with public policy or the fundamental principles of Indian law, and that alternative interpretations of evidence do not justify setting aside an award.

The Delhi High Court allowed the appeal under Section 37, reinstating the arbitral award. It held that the tribunal’s findings were well-reasoned and did not suffer from patent illegality or unconscionability. The judgment reinforces the principle of minimal judicial interference in arbitral awards, underscoring the autonomy of the arbitration process and the need to respect expert adjudication.

Key Takeaway

Section 34 of the Arbitration and Conciliation Act, 1996, provides the grounds for setting aside an arbitral award, including incapacity of a party, invalidity of the arbitration agreement, lack of proper notice, and conflict with public policy. Section 34(2A), introduced by the 2015 Amendment, addresses “patent illegality” for domestic awards, further narrowing the scope of judicial review. Courts must not re-evaluate the merits of the case or the evidence presented before the arbitral tribunal; the intent is to maintain the efficiency and effectiveness of arbitration, ensuring awards are final and binding save for specifically defined grounds.

© Nirka Law Advisory. All rights reserved. For queries, connect with us.