NLA Arbitration Newsletter
Key rulings from the Supreme Court, Delhi, Karnataka, Calcutta, and Bombay High Courts on the limits of judicial intervention in arbitration—covering referral court restraint, Section 37 appeals, contract interpretation, and prohibition on micromanagement of Arbitral Tribunals.

Supreme Court — Referral courts must not conduct detailed limitation enquiry under Section 11(6); that question belongs to the Arbitrator
The Supreme Court ruled that when considering a Section 11(6) petition for the appointment of an Arbitrator, referral courts should not delve into a detailed evidentiary investigation regarding whether the claims raised by the applicant are time-barred. Instead, they should leave that determination to the Arbitrator. The Court stated that the referral court should focus solely on determining whether the Section 11(6) application itself was filed within the three-year limitation period.
The judgment provided clarification on the earlier decision in Arif Azim Co. Ltd. v. Aptech Ltd., (2024) 5 SCC 313, which had established a two-pronged test: first, whether the Section 11(6) petition is barred by limitation; and second, whether the claims to be arbitrated are clearly dead and barred by limitation at the commencement of arbitration. The Court clarified the second prong—referral courts may recognise that claims are obviously invalid, but they need not conduct a detailed investigation to reach that conclusion. Where determination requires evidence, the question must be referred to the Arbitrator.
The Court drew support from In Re: Interplay Between Arbitration Agreements under A&C Act, 1996 & Stamp Act, 1899, (2024) 6 SCC 1, which emphasised that when evaluating claim validity on evidence, an Arbitral Tribunal—with access to comprehensive pleadings and evidence—is the appropriate authority, not the referral court. The Court noted that if a referral court can recognise lack of merit from minimal pleadings, it would be incongruous to doubt the Tribunal’s ability to reach the same conclusion with fuller material at the hearing stage.
The Court confirmed that the clarifications made in this judgment did not affect the core ratio of Arif Azim, which would continue to be fully enforced. The clarification was intended to align referral court conduct with contemporary arbitration principles and to prevent future conflicts between decisions.
Key Takeaway
At the Section 11(6) stage, the referral court’s only limitation enquiry is whether the appointment application itself was filed within three years. Determining whether the underlying arbitrable claims are time-barred requires evidence and is a matter for the Arbitrator, not the referral court. Referral courts should exercise restraint and decline to conduct detailed merit-based investigations into limitation.
Karnataka High Court — Ex-parte interim measures under Section 9 are appealable under Section 37, but interference is limited to rare circumstances
The Karnataka High Court Division Bench ruled that orders granting or refusing ex-parte interim measures under Section 9 of the Arbitration and Conciliation Act, 1996, are appealable under Section 37 of the same Act, regardless of whether they were filed before the Commercial Court.
The central question before the Court was whether the scope of “granting or refusing to grant any measure under Section 9” in Section 37 encompasses only final orders or also ex-parte interim measures. The Court examined Rule 9 of the High Court of Karnataka Arbitration (Proceedings before the Courts) Rules, 2001—which bears resemblance to Order XXXIX Rule 3 of the CPC—and found that ex-parte interim measures granted fall under Section 9. Section 37, which was amended in 2019 and opens with a non-obstante clause, lists specific appealable orders, and the Court held that this includes ex-parte interim measures.
The Court held that orders refusing ex-parte interim measures have the effect of final orders, as they definitively deny the relief sought, and are therefore appealable under Section 37. However, the extent of interference in such appeals is restricted. Appeals against orders granting ex-parte measures should only be entertained in rare circumstances, given that the aggrieved party always retains the option of applying to have the ex-parte order vacated.
The case was consequently remanded to the trial court to review the Section 9 application afresh. In the interim, the Petitioner was granted temporary protection, with a clarification that this temporary order should not be construed as a reflection on the merits of the Petitioner’s claim.
Key Takeaway
Ex-parte interim orders under Section 9 of the Arbitration Act are appealable under Section 37, as they can have the finality of a final order when they deny the requested relief. However, appellate courts must exercise caution: interference with orders granting ex-parte measures should be reserved for truly rare and exceptional circumstances, since the aggrieved party retains the remedy of seeking vacation of the ex-parte order before the original forum.
Delhi High Court — Appellate courts under Section 37 cannot independently re-evaluate the merits of an arbitral award
The Delhi High Court Division Bench emphasised that when considering an arbitration appeal under Section 37 of the Arbitration Act, the court’s role is restricted to determining whether the exercise of power under Section 34 has gone beyond the scope of that provision. Courts sitting in Section 37 appeals cannot conduct an independent evaluation of the merits of the award.
The Division Bench cited MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163, to confirm that the level of interference permissible under Section 37 cannot exceed the limits prescribed by Section 34. It also referred to NHAI v. M. Hakeem, (2021) 9 SCC 1, which clarified that Section 34 does not empower a court to modify or alter the terms of an award.
On the concept of “public policy of India” under Section 34(2)(b)(ii), the Court drew from ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, and S.V. Samudram v. State of Karnataka, (2024) 3 SCC 623, confirming that an award may be invalidated if it blatantly violates a statutory provision, lacks impartiality, disregards natural justice, or is contrary to the interests of India, justice, or morality.
On the specific facts, the Court found that the Petitioner’s argument that it had not signed the bill discounting agreements had not been raised during arbitration or Section 34 proceedings and was accordingly rejected. The Petitioner’s letter requesting an extension for payment was interpreted as an admission of liability. The decisions of both the Arbitrator and the Single Judge were grounded in evidence and free from legal error. The Arbitrator’s grant of pendente lite interest under Section 31(7)(a) was in accordance with the parties’ agreement. The appeal was dismissed, with parties directed to bear their own costs.
Key Takeaway
A Section 37 appeal is not a forum for re-examining the merits of an arbitral award. The appellate court’s role is confined to assessing whether the Section 34 court stayed within its prescribed scope. An independent merit review of the award is impermissible, and interference on public policy grounds is available only where the award blatantly violates a statutory provision or fundamental principles of law, justice, or morality.
Delhi High Court — Arbitral Tribunal’s contract interpretation is unreviewable on merits unless the interpretation is unreasonable; patent illegality is inapplicable to international commercial arbitration
The Delhi High Court Division Bench ruled that an Arbitral Tribunal has the authority to interpret a disputed contract, and such interpretation cannot be challenged under Section 34 of the Arbitration and Conciliation Act, 1996, unless it is deemed unreasonable.
In the underlying dispute, the sole Arbitrator analysed the evidence and concluded that the Respondent’s termination of the Contract of Affreightment (COA) was not justified under Clause 62. The Arbitrator found that the Respondent had no right to terminate the COA without valid reason and awarded compensation for losses caused by the breach. The Single Judge, however, partially allowed the Respondent’s Section 34 challenge—finding that the Arbitrator had misunderstood Clause 62 by incorrectly reading it with other provisions instead of construing it literally—and set aside the post-termination damages while upholding pre-termination damages.
On Division Bench appeal, the Court held that the COA’s language could not be interpreted in a purely literal, one-Clause-at-a-time manner. The entire contract and the parties’ intentions must be considered. Relying on Assam State Electricity Board & Ors. v. Buildworth (P.) Ltd., (2017) 8 SCC 146, and Associate Builders v. Delhi Development Authority, (2015) 3 SCC 49, the Court affirmed that an Arbitrator’s interpretation of a contract term cannot be the sole basis for overturning an award; such interpretation is unreviewable unless it is implausible.
Critically, the Division Bench noted that the Single Judge had failed to take into account that the matter involved an international commercial arbitration. For such arbitrations, Section 34(2A)—which permits challenge on the ground of patent illegality—is not available. Challenges must instead be assessed under the public policy of India standard, which, as clarified by Ssangyong Engineering and Construction Co. Ltd. v. NHAI, (2019) 15 SCC 13, does not encompass simple errors of contract interpretation.
The High Court accordingly allowed Noble’s appeal, set aside the Single Judge’s ruling, and reinstated the Arbitrator’s award in full, with each party to bear its own costs.
Key Takeaway
An Arbitral Tribunal’s interpretation of a contract is final unless it is so unreasonable or implausible as to be beyond the pale of legitimate construction. In international commercial arbitrations, the ground of patent illegality under Section 34(2A) is not available; a challenge must satisfy the narrower public policy standard, which does not encompass mere errors of interpretation. Isolated literal readings of individual clauses, divorced from the contract as a whole, will not suffice to set aside an award.
Calcutta High Court — LLP partners barred by res judicata from filing separate Section 37 appeal after the LLP’s appeal has been decided
The Calcutta High Court Single Bench ruled that an LLP and its partners are not permitted to file separate appeals under Section 37 of the Arbitration and Conciliation Act on the basis of the ‘separate legal entity’ principle. Where a prior appeal filed in the name of the LLP has been dismissed after full hearing, the individual partners are barred by res judicata from raising the same issues in a fresh Section 37 appeal.
The Court examined whether the scope of a challenge under Section 37 must mirror the scope of a challenge under Section 34. The Applicant argued that the breadth of an interim challenge under Section 37 should not exceed the breadth of a final challenge under Section 34. The High Court rejected this contention, noting that Section 37 is labelled ‘Appealable Orders’ and encompasses a range of orders beyond those governed by Section 34. A challenge against an order under Section 17 would be subject to the limits of Section 17, while an appeal against an order under Section 34 would be bound by the restrictions applicable to Section 34.
The Court also referred to GLS Foils Products (P) Ltd. v. FWS Turnit Logistic Park, 2023 SCC OnLine Del 3904, which emphasised the importance of respecting well-reasoned interim measures granted by an Arbitral Tribunal and the need for caution before interfering with such orders.
On the res judicata question, while acknowledging that an LLP is a distinct legal entity from its partners, the Court held that the Appellants (the LLP’s partners) had been given the opportunity to present their arguments in the earlier appeal and had availed of it. They were therefore bound by the outcome of that appeal. The principle of res judicata under Section 11 of the Code of Civil Procedure, 1908 precluded them from reopening the same issues in new proceedings. The High Court declined to address the merits of the appeal and dismissed it, with no order as to costs.
Key Takeaway
Although an LLP is a distinct legal entity from its partners, where the partners participated in a prior Section 37 appeal filed by the LLP and that appeal was dismissed after a full hearing, they cannot file a fresh Section 37 appeal raising the same issues. Res judicata bars the relitigation of issues already decided, and the doctrine applies regardless of whether the earlier proceedings were brought in the name of the entity or the individual partners.
Bombay High Court — Courts must not micromanage Arbitral Tribunals; Section 37(2)(b) intervention is strictly limited
The Bombay High Court Bench ruled that the court should refrain from excessive interference and micromanagement of proceedings pending before Arbitral Tribunals. The Court held that the extent to which the judiciary can intervene under Section 37(2)(b) of the Arbitration Act is strictly restricted in nature.
The Bench laid down the following principles:
(i) The supervising court will not interfere with the Arbitral Tribunal’s decision-making unless the Tribunal has acted in an arbitrary or capricious manner, or has disregarded established legal principles regarding the granting or denial of interlocutory injunctions.
(ii) Material on which the Tribunal has based its decision cannot be reassessed as long as the Tribunal has considered it and taken a reasonable view.
(iii) The court should not impede the Tribunal’s exercise of discretion so long as the Tribunal has made a reasonable and thoughtful decision, even if the court might have reached a different conclusion.
(iv) The interpretation of the provisions of a contract is primarily within the domain of the Arbitral Tribunal.
(v) The Court must refrain from excessive interference and micromanagement of ongoing proceedings before Arbitral Tribunals.
Citing Elster Instromet B.V. v. Mrunal Gandhi, Max Healthcare Institute Limited v. Touch Healthcare Private Limited, Karanja Terminal & Logistics (P) Ltd. v. Sahara Dredging Ltd., 2023 SCC OnLine Bom 594, and Raymond Ltd. v. Akshaypat Singhania, 2019 SCC OnLine Bom 227, the Court confirmed that once the Tribunal has considered the material and reached a plausible view, it cannot be reevaluated by the Court.
On the facts, the High Court found that the Arbitrator’s reading of Clauses 11 and 17 of the Partnership Deed—extending the earlier status quo order to additional scope—was reasonable and well-supported by the evidence before the Tribunal. However, the Court noted that an Arbitral Tribunal does not have the authority to appoint a Court Receiver; that requires direct court intervention. Finding that the Petitioner had presented a strong case of defiance of the Tribunal’s order by Respondent No. 1, the High Court appointed a Court Receiver itself.
Key Takeaway
Courts exercising jurisdiction under Section 37(2)(b) must not micromanage Arbitral Tribunals or second-guess their reasoned decisions. Intervention is reserved for cases of arbitrary or capricious conduct or clear disregard of established legal principles. A plausible, evidence-based Tribunal decision is insulated from judicial reassessment. Separately, certain reliefs—such as the appointment of a Court Receiver—lie beyond the Tribunal’s own powers and require courts to step in directly.
© Nirka Law Advisory. All rights reserved. For queries, connect with us.