The Ministry of Finance’s 3 June 2024 Guidelines, carried into the highway sector by MoRTH’s 12 January 2026 Circular, mark a shift from a predominantly arbitration-oriented model towards a value-based and settlement-oriented framework. For highway contractors and concessionaires, the central question may now be whether a dispute, by its value and character, is arbitrable at all.

Dispute resolution has always been a critical component of India’s highway sector. The Government’s approach to resolving such disputes has, over time, moved through several mechanisms, including Dispute Resolution Boards, conciliation and institutional arbitration. The National Highways Authority of India (“NHAI”) itself established Conciliation Committees of Independent Experts (“CCIEs”) in 2017 to facilitate amicable settlement. By the end of FY 2023-24, NHAI reported that 211 out of 326 cases referred to the CCIE mechanism had been successfully resolved, involving settlements of approximately ₹18,327 crore against claims of ₹59,772 crore.1
Against this background, the Ministry of Finance (“MoF”), Department of Expenditure, issued its Office Memorandum dated 3 June 2024,2 titled Guidelines for Arbitration and Mediation in Contracts of Domestic Public Procurement. The Guidelines marked a significant change in the Government’s approach: arbitration was no longer to be routinely or automatically incorporated into Government procurement contracts, particularly large contracts. As a general norm, arbitration was to be restricted to disputes having a value below ₹10 crore.
The policy was subsequently carried into the highway sector. On 12 January 2026, the Ministry of Road Transport and Highways (“MoRTH”) directed that the existing dispute-resolution provisions in the Model Concession Agreements and contract documents for BOT (Toll), HAM and EPC projects be replaced by a modified dispute-resolution chapter. MoRTH expressly stated that the revised provisions were issued pursuant to the MoF Guidelines.3
The significance of this development goes beyond the mere substitution of one dispute-resolution mechanism for another. It represents a shift from a predominantly arbitration-oriented model towards a value-based and settlement-oriented framework. For highway contractors and concessionaires, the central question is therefore no longer merely whether a contractual dispute is capable of being arbitrated. The more fundamental question may now be: Is the dispute, by its value and character, arbitrable under the revised contractual framework at all?
The modified dispute resolution framework provides as follows:
The MoF Guidelines provide the starting point for understanding the reform.
The 3 June 2024 Office Memorandum recognises the conventional advantages associated with arbitration—speed, technical expertise, procedural flexibility and finality. However, the Ministry observed that the experience of Government entities had not consistently reflected these advantages. According to the Guidelines, arbitration involving Government entities had frequently become lengthy and expensive, and arbitral awards were often challenged before courts. As a result, arbitration had, in the Government’s assessment, sometimes operated as an additional layer of litigation rather than as a substitute for litigation.
The most consequential provision of the MoF Guidelines is the value threshold. The Guidelines state that arbitration should not be routinely or automatically included in Government procurement contracts, particularly large contracts. Where arbitration is included, it may, as a norm, be restricted to disputes with a value below ₹10 crore. Crucially, the Ministry clarifies that the ₹10 crore threshold refers to the value of the dispute and not the value of the underlying contract.
This distinction is particularly important for highway projects. For example, a highway EPC contract may itself have a value of ₹500 crore, ₹1,000 crore or substantially more. That does not mean that every dispute arising from that contract is necessarily outside arbitration. The relevant consideration is the value of the particular dispute.
The monetary value of the dispute therefore becomes a determinant of the dispute-resolution forum. This represents a fundamental change in risk allocation because highway disputes are frequently high-value.
The MoRTH Circular dated 12 January 2026 expressly states that, pursuant to the MoF Guidelines, the existing dispute-resolution article in the contractual documents for BOT (Toll), HAM and EPC projects is to be replaced by the modified chapter. It further states that the new provisions override the existing provisions for these projects, subject to the treatment of ongoing arbitrations under the earlier provisions.4
The revised contractual framework establishes a substantially different structure.
The new framework may have a significant practical impact on delay-related disputes. A contractor may first need to establish its contractual entitlement, such as whether a delay was attributable to the Authority and whether it is entitled to an extension of time, before determining the resulting monetary consequences.
This becomes particularly important because declaratory and non-monetary disputes are excluded from arbitration. Where a claim involves both entitlement and quantum, the characterisation of the dispute may therefore affect the forum available to the parties. This makes careful claim formulation and documentation increasingly important under the revised framework.
The revised framework makes early claim formulation and proper documentation more important for contractors. Claims should clearly establish the contractual obligation, breach or event, resulting delay, impact on the project, additional costs and quantum, supported by contemporaneous records.
The importance of evidence is evident from NHAI’s recent experience. In May 2026, NHAI reported successfully defending a claim of approximately ₹174.49 crore relating to the Kamrej–Chalthan section of NH-48, with the tribunal ultimately awarding only ₹54 lakh. NHAI attributed the outcome, among other factors, to digital project monitoring and evidence-based contract management.5
For high-value disputes falling outside arbitration, conciliation and mediation may become the primary route to resolution. Contractors will therefore need to enter settlement proceedings with a clear assessment of liability, evidence, quantum and their realistic settlement position. The impact extends to HAM and BOT projects, where disputes relating to authority default, change in law, change of scope, delays, termination or revenue loss can affect the entire financial model of a concession. The exclusion of certain high-value disputes from arbitration may therefore affect both contractual risk and project bankability, since lenders also consider the certainty and timing of recovery of contractual claims.
The framework also raises an important issue for existing contracts. The MoRTH Circular dated 12 January 2026 provides for the modified dispute-resolution provisions to apply to existing BOT (Toll), HAM and EPC projects, while ongoing arbitrations continue under the earlier mechanism. This raises the question of whether an agreed dispute-resolution mechanism can subsequently be altered through an administrative circular. The answer will depend on the contract terms, the stage at which the dispute has arisen, whether arbitration has commenced, and whether the parties have consented to the change. The issue is significant because the dispute-resolution clause forms part of the parties’ contractual risk allocation. Any change to the agreed mechanism can therefore have wider consequences for the legal and financial risks of a highway project.6
Thus, there is a shift from dispute adjudication to dispute avoidance. This philosophy is already visible in NHAI’s CCIE and DRB mechanisms. NHAI has expressly stated that DRBs were established to obtain first-hand information concerning site activities and resolve disputes before they escalated to arbitration or litigation.
The Ministry of Finance’s 3 June 2024 Guidelines and MoRTH’s 12 January 2026 implementation mark a significant shift in the approach to contractual disputes in India’s highway sector. The reform moves away from relying primarily on arbitration towards early identification, structured conciliation and mediation, with arbitration available only in limited cases.
For highway projects, the success of this model will ultimately depend on its implementation. Faster dispute resolution alone may not reduce the dispute burden if the underlying causes, particularly delays in land acquisition, approvals, project planning and contract administration remain unresolved. The real test, therefore, is whether the new framework can not only settle disputes earlier but also prevent them from escalating into major disputes in the first place.