NLA Arbitration Newsletter

Arbitration Newsletter — October 2025

Key rulings this month from the Delhi and Madras High Courts, the Bombay High Court, and the Supreme Court — covering enforcement of foreign awards under Section 48, the primacy of statutory MSMED arbitration over contractual clauses, and execution of awards pending Section 37 appeals without a stay.

NLA Arbitration Newsletter — October 2025

Roger Shashoua & Ors. v. Mukesh Sharma & Ors., 2025 SCC OnLine Del 5773

Delhi High Court enforces ICC foreign awards despite objections on jurisdiction and public policy, reaffirming India’s pro-enforcement stance under Section 48.

The dispute traces back to a Shareholders’ Agreement (SHA) executed in July 1998, regulating the affairs of International Trade Expocentre Ltd. (ITEL), a joint venture created to establish and operate an exhibition centre in Noida. The SHA granted equal shareholding and management control to two groups, represented respectively by the Petitioners and the Respondents. It contained elaborate provisions governing governance, transfer restrictions, and resolution of deadlocks. Critically, it incorporated a broad arbitration clause providing for arbitration under ICC Rules with London as the seat.

Disputes erupted over competing businesses, disputed share issuances, and allegations of siphoning of funds. In 2005, arbitration was invoked under the ICC framework. The tribunal issued four awards: a jurisdictional award in 2007 confirming the SHA as a binding contract; a costs award later that year; a partial final award in 2010 directing transfer of Respondents’ shares to the Petitioners due to breaches; and a final award in 2011 reiterating share transfer directions and awarding further costs. The Petitioners sought enforcement of the 2010 and 2011 awards before the Delhi High Court.

The Respondents resisted enforcement on multiple grounds. They argued that the tribunal exceeded its mandate by ordering transfer of shares — relief which, they contended, only the Company Law Board/NCLT could grant under provisions on oppression and mismanagement. They also claimed the SHA was merely a preliminary document and not binding, that successors and assigns could not be bound, and that the tribunal’s orders amounted to expropriation of shares contrary to Indian public policy. Limitation objections were raised as well, asserting that enforcement petitions were filed beyond the three-year limit under Article 137 of the Limitation Act.

The Court began by addressing limitation. Although acknowledging that Article 137 governs enforcement of foreign awards, it condoned the delay. It emphasised the legal uncertainty that prevailed for years after Bhatia International v. Bulk Trading S.A. and BALCO v. Kaiser Aluminium, when courts entertained Section 34 challenges to foreign awards. The Supreme Court’s later ruling in Roger Shashoua v. Mukesh Sharma, 2017 14 SCC 722, clarified that Indian courts had no jurisdiction over such foreign-seated arbitrations. Given this shifting legal landscape, the Court found sufficient cause to condone delay.

Turning to jurisdiction, the Court emphasised that the SHA contained a broad clause covering disputes concerning the validity, interpretation, implementation, or breach of its provisions. The tribunal had carefully reviewed contemporaneous correspondence, financial transactions, and share transfers, concluding that the SHA was binding and extended to successors and permitted assigns. The Court accepted this reasoning, observing that the SHA expressly contemplated inclusion of nominees and transferees, thereby binding parties like Rodemadan, Stancroft, and ITE. Thus, the tribunal’s findings that successors and assignees were bound could not be re-opened at the enforcement stage.

The more significant objection was that the tribunal exceeded its mandate by ordering transfer of shares. The Court rejected this, noting that the relief flowed directly from contractual obligations under the SHA. Article 4.7 contemplated arbitration in the event of board deadlocks, and the tribunal was empowered to craft effective remedies to resolve the unworkable deadlock. Moreover, both parties had themselves proposed buyout solutions during proceedings, undermining their later contention that such relief was beyond the tribunal’s powers.

On public policy, the Court reiterated the settled principle that Section 48 provides only narrow grounds for resisting enforcement. Following Renusagar Power Co. Ltd. v. General Electric Co. and Shri Lal Mahal Ltd. v. Progetto Grano SPA, it held that public policy objections are limited to violations of fundamental policy of Indian law, basic notions of morality or justice, or fraud and corruption. The Court stressed that errors of fact or law cannot bar enforcement. The allegation of expropriation was dismissed, with the Court observing that Respondents had themselves diluted Petitioners’ shareholding in violation of the SHA. Far from being inequitable, the tribunal’s orders restored balance by directing share transfers proportionate to investments made.

The Court also highlighted India’s international obligations under the New York Convention. Section 48 mirrors Article V of the Convention, which envisages a pro-enforcement bias. Judicial review of foreign awards is tightly circumscribed, ensuring that national courts do not sit in appeal over arbitral findings. The Delhi High Court emphasised that enforcing the ICC awards advanced India’s public policy by protecting foreign investors and reinforcing ease of doing business. In conclusion, the Delhi High Court dismissed all objections and declared the foreign awards enforceable under Sections 47 and 49, imposing costs on the Respondents for protracted resistance.

Key Takeaway

Section 48 of the Arbitration and Conciliation Act, 1996 embodies India’s commitment to the New York Convention, restricting judicial review of foreign arbitral awards to narrow grounds such as incapacity, invalidity of the arbitration agreement, breach of natural justice, excess of jurisdiction, or conflict with India’s fundamental public policy. Courts cannot re-examine merits or factual findings. Once enforceability is confirmed under Section 49, the award is deemed a decree of the court and executed accordingly, reflecting India’s pro-enforcement bias in international arbitration.

PI Opportunities Fund & Ors. v. Financial Software and Systems & Ors., 2025 SCC OnLine Mad 7113

Madras High Court enforces SIAC foreign award, rejecting objections based on buyback restrictions, election of remedies, waiver, and fraud under Section 48.

The petitions arose from enforcement proceedings relating to a foreign arbitral award dated 5 July 2024, rendered under SIAC Rules in Singapore, in disputes between private equity investors and the promoters of Financial Software and Systems (FSS), a major Indian digital payments company. The investors had acquired shares under a Share Acquisition and Shareholders’ Agreement (SASHA) of 2014, as amended in 2018. The SASHA included a detailed “exit waterfall” mechanism (Clause 19), offering investors secondary sale, buyback, IPO, or strategic sale as successive exit routes.

When efforts to secure a Qualified IPO or a secondary sale failed, the investors issued notices in 2020–21 to trigger their rights, alleging that the promoters materially breached their obligations by failing to secure an exit. Before the arbitral tribunal, the investors claimed damages equivalent to the contractual exit price (Clause 19.1) and sought specific performance of the right to implement a strategic sale (Clause 19.6). The promoters disputed these claims, arguing that no absolute obligation existed under Clause 19.1, that investors had waived their rights by participating in a split sale process, that remedies under Clause 24.6 were mutually exclusive, and that liability was capped under Clause 22.

The tribunal issued a detailed award granting damages equivalent to the exit price and directing that, if such damages were not paid within 90 days, the investors could proceed with a strategic sale. To prevent double recovery, the tribunal further required surrender of shares if damages were paid. On clarification, the tribunal held that remedies under Clause 24.6 were alternative, and that only one remedy — damages or strategic sale — could ultimately be enforced.

Before the Madras High Court, the promoters resisted enforcement under Section 48. They argued that: (i) the award amounted to an illegal “buyback” of shares, violating Sections 66–68 of the Companies Act, 2013; (ii) investors had impermissibly pursued both termination and strategic sale, contrary to the doctrine of election; (iii) by participating in split sale discussions, investors waived their rights under Clause 19.1; (iv) the tribunal failed to consider affirmative vote matters; (v) the award violated provisions of the Specific Relief Act; and (vi) investors concealed an Ernst & Young report on FSS’s financials, amounting to fraud.

The High Court rejected each objection, emphasising the narrow scope of Section 48. On the buyback issue, the Court distinguished between “buyback” under Section 68 of the Companies Act and “surrender” of shares upon payment of damages. It noted that the award directed damages against individual promoters, not a company-led buyback, and that surrender was incidental to prevent double recovery. Statutory provisions regulating capital reduction or buyback did not by themselves represent fundamental policy of Indian law.

On the doctrine of election, the Court observed that the investors had invoked both remedies simultaneously, and the tribunal had chosen to give effect to strategic sale while allowing termination rights to lapse — this did not violate natural justice. Citing Vijay Karia v. Prysmian Cavi and Vedanta v. Government of India, the Court reiterated that Section 48 does not permit reopening contractual interpretation. The waiver objection was similarly dismissed: Clause 29.5 of SASHA required any waiver to be in writing, and participation in split sale discussions did not amount to waiver. The Singapore High Court, acting as the seat court, had already rejected this objection, and principles of transnational issue estoppel prevented its re-litigation.

On alleged breach of the Specific Relief Act, the Court emphasised that the 2018 amendments made specific performance the rule, applicable retrospectively; granting damages coupled with strategic sale did not contravene Indian law. The fraud objection, based on non-disclosure of the EY report, was also rejected — Respondents were aware of the report during arbitration yet failed to raise it, and mere allegations without substantial evidence do not meet the high threshold under Section 48(2)(b)(i).

Reaffirming settled law through Renusagar v. GE (1994), Shri Lal Mahal v. Progetto Grano (2014), and Vijay Karia v. Prysmian (2020), the Court reiterated that “public policy” under Section 48 must be construed narrowly. Enforcement may be refused only if the award is induced by fraud, violates fundamental policy of Indian law in a non-derogable way, or shocks basic notions of justice or morality. In conclusion, the Court declared the award enforceable and imposed costs of INR 25 lakh on the objecting respondents for raising untenable objections and delaying enforcement.

Key Takeaway

Exit mechanisms in shareholder agreements — such as secondary sale, buyback, IPO, or strategic sale — are enforceable contractual rights. Arbitral tribunals may grant damages for breach of these obligations and couple them with remedies like share surrender or strategic sale to prevent double recovery. Such contractual remedies, when crafted within the framework of the agreement, do not amount to statutory buybacks under the Companies Act, 2013. Objections under Section 48 cannot be used to re-litigate issues already decided by the tribunal or the seat court.

GEA Westfalia Separator India Pvt. Ltd. v. SVS Aqua Technologies LLP, 2025 SCC OnLine Bom 3157

Bombay High Court declines jurisdiction over MSMED arbitral award challenges, holding that statutory arbitrations under the MSMED Act are territorially anchored to the Facilitation Council where the supplier is located.

The petitions arose under Section 34 where GEA Westfalia Separator India Pvt. Ltd. (“GEA”) sought to set aside awards dated 18 November 2024 rendered by the Micro and Small Enterprises Facilitation Council, Pune (“Facilitation Council”). The Facilitation Council, acting under Section 18 of the MSMED Act, 2006, had directed GEA to pay dues and interest to SVS Aqua Technologies LLP (“SVS Aqua”) arising from a manufacturing and supply agreement of November 2019.

At the threshold, SVS Aqua raised an objection to territorial jurisdiction. It argued that since arbitration was conducted under Section 18 before the Facilitation Council in Pune, challenges under Section 34 must lie before the principal civil court in Pune. GEA countered that Clause 23 of the contract provided for arbitration “in Mumbai” under ICADR Rules, implying Mumbai as the “seat” of arbitration and conferring jurisdiction on the Bombay High Court.

The Court identified this as the preliminary point. Clause 23 provided for disputes to be resolved “exclusively by arbitration in Mumbai” under ICADR Rules. However, the arbitration culminating in the impugned awards was not held under Clause 23 but under the statutory mechanism in Section 18 of the MSMED Act. Once conciliation failed, Section 18 deemed an arbitration agreement to exist, and the Facilitation Council assumed jurisdiction. The proceedings were therefore statutory arbitrations, independent of the contractual clause.

The Court emphasised that Section 18(4) of the MSMED Act confers jurisdiction on the Facilitation Council within whose territory the supplier is located, overriding contrary agreements. SVS Aqua being based in Pune meant the Pune Facilitation Council was the statutory forum. The arbitration was held entirely in Pune under the MSMED Act, not under ICADR Rules. The impugned awards were thus products of statutory arbitration, not of the contractual clause.

The Court distinguished “seat” and “venue” in arbitration law. Under contractual arbitration, a seat determines supervisory court jurisdiction. But here, there was no arbitration under Clause 23. Pune was not merely a venue but the statutory seat under Section 18, fixed by law where the supplier operates. GEA’s attempt to invoke Clause 23 to shift jurisdiction to Mumbai was “untenable,” because the clause was never acted upon. The agreement also lacked any exclusive jurisdiction clause vesting court jurisdiction in Mumbai.

GEA relied on Gammon Engineers & Contractors v. Rohit Sood, (2024) SCC OnLine Bom 3304, where the Bombay High Court upheld party autonomy in choosing Mumbai courts despite an MSMED arbitration elsewhere. The Court distinguished that precedent — in Gammon Engineers the parties had an explicit exclusive jurisdiction clause naming Mumbai courts; the present agreement had no such clause. Citing Ravi Ranjan Developers v. Aditya Kumar Chatterjee, 2022 SCC OnLine SC 568, the Court reiterated that precedents cannot be abstracted from their factual setting.

In conclusion, the Court held that the relevant arbitration agreement was the statutory agreement deemed under Section 18 of the MSMED Act, the seat was statutorily fixed as Pune, and challenges under Section 34 lay before the competent civil court in Pune. The petitions before the Bombay High Court were dismissed for want of jurisdiction.

Key Takeaway

Arbitrations under Section 18 of the MSMED Act operate through a statutory arbitration agreement, deemed to exist once conciliation fails. The Facilitation Council where the supplier is located has territorial jurisdiction to conduct such proceedings. This statutory seat prevails over any contractual arbitration clause, unless the agreement expressly contains an exclusive jurisdiction clause for courts. Challenges under Section 34 must be filed before the courts at the place where the Facilitation Council conducted the arbitration — contractual designations of seat or arbitral rules are irrelevant once Section 18 is invoked.

Chakardhari Sureka v. Prem Lata Sureka & Ors., Civil Appeal No. 11840 of 2025

Supreme Court clarifies that execution of arbitral awards cannot be deferred merely because a Section 37 appeal is pending — unless an interim stay is specifically granted.

The dispute arose out of an arbitral award challenged under Section 34. The Section 34 application was dismissed, leaving the award intact. The award-debtor then filed an appeal under Section 37 of the Act. Although that appeal remained pending, no interim stay was granted by the appellate court. In the meantime, the award-holder initiated execution proceedings before the Delhi High Court.

The Execution Court adjourned the matter, observing that since a Section 37 appeal was pending, it would not proceed with enforcement. The award-holder carried the matter to the Supreme Court, contending that such deferment was impermissible in the absence of a stay order.

The appellant award-holder argued that Section 36 of the Arbitration Act provides the statutory framework for enforcement. Under Section 36(2), mere filing of an application under Section 34 does not render an award unenforceable unless the court grants a stay. Section 36(3) empowers the court to grant stay on conditions, but until such stay is ordered, the award is enforceable as if it were a decree. This principle, the appellant argued, applies equally at the appellate stage — a pending Section 37 appeal without stay cannot freeze execution.

The respondents contended that certain objections regarding executability of the award were still open and should be considered by the Execution Court, and that the pendency of the Section 37 appeal justified deferring enforcement to avoid prejudice.

The Supreme Court rejected this line of reasoning. It observed that once a Section 34 petition is dismissed, the award becomes enforceable. The pendency of a Section 37 appeal by itself does not alter the award-holder’s right to enforce. Section 36 makes it clear that the award remains enforceable unless stayed. To hold otherwise would defeat the pro-enforcement framework of the Arbitration Act, which aims to minimise delay in realisation of awards.

The Court held that while the Execution Court is empowered to examine objections relating to executability in accordance with law, it cannot decline to proceed merely because a Section 37 appeal is pending. Unless an interim order is passed in the appellate proceedings, the Execution Court must proceed with enforcement. The decision does not prevent the award-debtor from raising issues of executability under the Code of Civil Procedure, 1908, but the pendency of appellate proceedings cannot be used as a blanket shield to defer enforcement. The Court allowed the appeal, clarifying that the Execution Court is free to proceed with enforcement subject only to any interim orders in pending appellate proceedings.

Key Takeaway

Under Section 36 of the Arbitration and Conciliation Act, 1996, an arbitral award remains enforceable as a decree unless stayed by the court. The mere pendency of an appeal under Section 37 does not bar execution proceedings. Execution Courts must proceed with enforcement unless an interim stay is specifically granted — appellate proceedings without a stay order cannot be used as a blanket shield to defer realisation of an arbitral award.

© Nirka Law Advisory. All rights reserved. For queries, connect with us.